This extension on an existing warehouse to procure an additional 8630 pallet locations was awarded to Palian (Pty) on Tender.

The standard manufacturing lead time required was 4 weeks from date of order, with one month’s installation period. Some delays were experienced during the installation process, due to other contracting requirements – which delayed the site with a week, but Palian (Pty) Ltd accommodated the customer and still delivered & installed within the required time frame. The only challenges were working in a constant “building progress” environment. Site access was shared with other contractors and some extra planning was required.

Working closely with the Warehouse managers was crucial and the project was completed within the specified dates. Another satisfied customer which we are looking forward to building up yet another long-standing successful business relationship with.